top of page
fermenters.jpg
probiotics-preview.jpg

Trust us with your project
with confidence

As one of the earliest and professional bioreactor manufacturers in China, Lab1st has thousands of fermentation system in operation all over the world. We are delight to share some of cases with you. Here, take Project LB-193 for an instance:

LB-193 project is for biotechnological production, which is engaged in the cultivation of industrial strains of beneficial microorganisms, scaling the technology from a test tube to an industrial volume, such as probiotic, E. coli cultures, etc. Now it’s in operation at Tomsk, Russia, a company who has 20-year experience in the development of biotechnological products.

The whole system’ main equipment as follow:

Storage capacities.jpg

1500L Fermenter

5 sets

fermentation line.jpg

Tubular centrifuge

3 sets

fermenters .jpg

200L Bioreactor

1 set

lyophilization site.jpg

Supplementary tank

7 sets

process control.jpg

Control panel

PLC

high pressure homogenizer.jpg

Homogenizer

1 set

Project Discussion

In the early stage communication of LB-193 project, our sales and engineering teams had many phone calls and video conferences with customers to discuss the project details. And we showed the customer around our factory..

01

截屏2022-11-17 19.58.16.png
Layout.png

Drawing Design

Having confirmed all customer’ needs and process operation conditions, our senior engineering team started to make electrical schematic diagram, PID drawings, 3D drawings, layouts and mechanical drawings, like tank design, pipe design and so forth.

02

Production

In this project, it includes 5 sets 1500L bioreactors, 1 set 200L bioreactor, 1 set 200L bioreactor, 3 sets tubular centrifuges, 7 sets supplementary tanks, 1 set viscolizer and all necessary accessories. The production lasted 6 months.

03

production.jpg
QC.jpg

Quality Control

This is your Project description. Provide a brief summary to help visitors understand the context and background of your work. Click on "Edit Text" or double click on the text box to start.

04

Delivery

In the early stage communication of LB-193 project, our sales and engineering teams had many phone calls and video conferences with customers to discuss the project details. And we showed the customer around our factory..

05

DELIVERY.jpg
istallation.jpg

Installation

Bioreaction system is a relatively complex device. During the installation and operation of the equipment, people with certain experience are required. We not only provide complete online installation support, such as installation instructions, installation videos, etc., but also provide on-site installation services. In this project, our installation and commissioning team flew to Tomsk to help customers install and make commissioning operation. They stayed in Russia for two months.

06

Commissioning

In the early stage communication of LB-193 project, our sales and engineering teams had many phone calls and video conferences with customers to discuss the project details. And we showed the customer around our factory..

07

IMG_0733 2.JPG

Get an Instant Quote